Timeline

Signed Purchase Agreement: 8/24/2012
Submitted Loan Application to NVR: 9/4/2012
Structual and Non-Structural Options Locked in: 9/8/2012
Cable & wiring selections meeting: 9/14/2012
Additional documents requested to process loan:  9/19/2012
Loan submitted to Underwriting for Approval:  9/20/2012
Loan denied by NVR:  10/19/2012
Loan submitted to Third Party "Broker" for approval: 10/23/2012
Flooring selections meeting:  9/20/2012
Loan Approved by "Broker": 10/31/2012
Preconstruction Meeting:  11/7/2012
Construction begins (Lot Grading & Excavation):  11/19/2012
Pre-drywall Walkthrough: 1/2/2013
Loan submitted to NVR (again):  1/3/2013
Pre-settlement Walkthrough:  2/21/2013
Rate Locked (3.25%):  2/25/2013
Closing: 2/25/2103
Loan Approved by NVR:  3/4/2013
Closing: 3/15/2013



1 comment:

  1. First....Congrats on your new home!!! I hope you and your family are enjoying your blessings. I am in the process of building my first home too and decided like you and other share my story and blog my experience. I have a question for you? I am trying to revise my page and I want my blog to have a similar setup like you have with the tabs that show the timelines, floor plan and all that I've chosen to. However, I am having a difficult time doing so. Is it possible you can guide me on how to add the tabs to my page please. Thank you for your help in advance and God bless!